Based on the number of customers, the average number of customers, and the time given, the process is I = 10 customers, R = 20 customers per hour, T = 30 minutes.
I is the average number of customers at any given point in time which is ten = 10.
R is the number of customers that the bank gets per hour which is 20 customers.
T is half the number of minutes that the normal number of customers take to walk into the bank:
= 60 minutes / 2
= 30 minutes.
Find out more on process metrics at https://brainly.com/question/26511304.