Diners are served in a process with two resources. The first resource has a capacity of 1.1 diners per hour. The capacity of the second resource is 1.5 diners per hour. Demand for this process is 0.9 diners per hour.Instruction: Round your answer to three decimal places. What is the cycle time of this process (in minutes)

Sagot :

The cycle time of this process for the firm is 2.89.

What is a Cycle Time?

This refers to the average time between the start of production of one unit and the start of production of the next unit of production

Cycle Time = Net time available to work / Customer demand

Cycle Time = 1.1 + 1.5 / 0.9

Cycle Time = 2.88888888889

Cycle Time = 2.89.

Therefore, the cycle time of this process for the firm is 2.89.