The Critical Path is B-D-E-G. See the definition of Critical Path below.
What is the meaning of Critical Path?
Critical Path refers to the order of steps that determines the shortest amount of time required for a task.
What is the total project completion time?
The Total Project completion time is 34 days. This is derived from the AON Network for the problem. See the attached.
What is an AON Diagram?
AON (Activity - on -Node) diagram is a fundamental kind of logic diagram utilized for activity scheduling.
What is the slack time for each individual activity?
Slack time is the duration of a job that can be postponed without affecting other tasks or the project's completion deadline.
Hence, the slack time for EACH activity is given as follows:
A : 22-8 = 14
B : 0
C : 34 -19 = 15
D : 0
E : 0
F : 34-19 = 15
G : 0
Learn more about Critical Path at:
https://brainly.com/question/15091786
#SPJ1