The objective of the project planning process is the development of a Baseline Project Plan and Project Scope Statement.
Baseline Project Plan and Project Scope Statement
- An accepted version of your project's scope, as described in a scope statement, work breakdown structure, and WBS dictionary, is called a scope baseline.
- Project progress is tracked and results between real and planned are compared using the scope baseline as a reference.
- A project scope statement gives a thorough explanation of the work that must be done to produce the project's output on time and within budget.
- It also defines the project's boundaries. All work and only work necessary to finish the project within the budget is included in the project scope statement.
- The scope statement should be as long as necessary to mitigate the project's main risks.
To learn more about Baseline Project Plan and Project Scope Statement refer to:
https://brainly.com/question/14498531
#SPJ4