The better Project is Project S having a NPV of $17.968 and IRR of 12.10 %
IRR:
- An approach to capital budgeting that is used to assess the profitability of a project is the discounted payback time. Internal rate of return is one of these capital planning strategies (IRR).
- This rate of return corresponds to the point at which a project's net present value equals zero. Since it does not account for any outside forces, such as inflation, they call it internal.
The calculator's capabilities will be utilized to determine the IRR,
Project S
- CF0 = (1,000)
- CF1 = 882.62 & F01 = 1
- CF2 = 250 & F02 = 1
- CF3 = 15 & F03 = 1
- CF4 = 5 & F04 = 1
- I = 10.5%
- [NPV] [CPT]
- The NPV is $17.968
- [IRR] [CPT]
- The IRR will come as 12.10%
- Project L
- CF0 = (1,000)
- CF1 = 0 & F01 = 1
- CF2 = 260 & F02 = 1
- CF3 = 420 & F03 = 1
- CF4 = 732.87 & F04 = 1
- I = 10.5%
- [NPV] [CPT]
- The NPV is $15.78
- [IRR] [CPT]
- The IRR will come as 11.03%
- The better Project is Project S having a NPV of $17.968 and IRR of 12.10%
Learn more about IRR here brainly.com/question/7920964
#SPJ4
We value your presence here. Keep sharing knowledge and helping others find the answers they need. This community is the perfect place to learn together. IDNLearn.com is dedicated to providing accurate answers. Thank you for visiting, and see you next time for more solutions.