Which document is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?

Sagot :

The project charter often mentions planned project start and end dates, which serve as the starting points for a more detailed schedule.

A project charter is a proper brief document that states a task exists and gives challenge managers written authority to begin paintings. An undertaking charter record describes an assignment to create shared expertise of its dreams, goals, and aid requirements before the assignment is scoped out in detail.

In project control, a challenging charter, undertaking definition, or assignment assertion is an announcement of the scope, objectives, and members of a task.

Project charter units out the scope, targets, and those worried about the challenge. This formal file makes use of all that facts to authorize the task. So the constitution shall we the mission manager use organizational and outsourced sources to complete the assignment.

Learn more about the project charter here: https://brainly.com/question/14544849