Describe how crashing and fast tracking can be used to compress a project schedule. What limitations could there be with each of these methods?

Sagot :

Techniques for compressing the schedule include Crashing and Fast Tracking. You use them to shorten your timetable and to meet a specific scheduling objective. Fast-tracking entails carrying out two tasks concurrently, even though they wouldn't typically be.

How does fast-tracking differ from crashing to compressing a project schedule?

In conclusion, the distinctions between crashing and fast tracking are as follows: Fast-tracking entails running tasks simultaneously, whereas crashing entails adding resources to a project. The increased danger is associated with quick tracking, but the increased expense is associated with crashes.

What limitations could there be with each of crashing and fast-tracking?

Fast-tracking is free but increases the risk associated with your project. Adding more resources to your project is referred to as "crashing." Having a crash costs more money. To compress your calendar the most while spending the least amount of money, you should crash such activities. method:

Learn more about crashing and fast-tracking methods: https://brainly.com/question/14478482