Ask questions, share knowledge, and connect with a vibrant community on IDNLearn.com. Our experts provide timely and accurate responses to help you navigate any topic or issue with confidence.

1.
Six workers working at the same rate can dig a drainage channel in 3 da
How long will it take the following workers (working at the same rate)
complete the same job?
(a) 4 workers
(b) 8 workers


Sagot :

Final answer:

To find out how long it takes different numbers of workers to complete a job based on worker-days when 6 workers can finish it in 3 days.


Explanation:

To determine how long it would take a different number of workers to complete the same job, you can use the concept of 'worker-days.' Since 6 workers can finish the job in 3 days, the total worker-days needed is 6 workers * 3 days = 18 worker-days.

(a) For 4 workers: If the total worker-days needed is 18 and now there are 4 workers, the number of days would be 18 worker-days / 4 workers = 4.5 days to finish the job.

(b) For 8 workers: Similarly, with 8 workers, it would take 18 worker-days / 8 workers = 2.25 days to complete the job.


Learn more about Time calculcations for completing a job with different number of workers here: