You are working on the implementation of the smart traffic signal. The project has been completed about 2 months later than expected at a cost 2.5% lower than the budget. Which one of the following will you not undertake?
a. Resolve outstanding invoices
b. Obtain all outstanding operational documents
c. Meet all regulatory requirements
d. Calculate qualitative risk for the project