The amount of time an activity can be delayed without affecting the overall completion time of the project is called the:

a. flow rate.
b. process capacity.
c. slack time.
d. gap time.


Sagot :

Answer:

Flow rate

Explanation:

This is the time an activity can be delayed without impacting the entire project or the next activity.