Find trusted answers to your questions with the help of IDNLearn.com's knowledgeable community. Ask anything and receive well-informed answers from our community of experienced professionals.
Sagot :
Let's solve this step-by-step.
1. Calculate total manufacturing overhead costs:
The estimated manufacturing overhead costs for Department 1 are \[tex]$2,530,000 and for Department 2 are \$[/tex]900,000.
[tex]\[ \text{Total manufacturing overhead costs} = \$2,530,000 + \$900,000 = \$3,430,000 \][/tex]
2. Calculate total direct labor hours (DLH):
The estimated direct labor hours for Department 1 are 168,000 hours and for Department 2 are 110,000 hours.
[tex]\[ \text{Total direct labor hours} = 168,000 \text{ DLH} + 110,000 \text{ DLH} = 278,000 \text{ DLH} \][/tex]
3. Calculate the plantwide overhead rate:
The plantwide overhead rate is calculated by dividing the total manufacturing overhead costs by the total direct labor hours.
[tex]\[ \text{Plantwide overhead rate} = \frac{\text{Total manufacturing overhead costs}}{\text{Total direct labor hours}} = \frac{\$3,430,000}{278,000 \text{ DLH}} = \$12.34 \text{ per DLH} \][/tex]
4. Calculate total direct labor hours needed for the expected production:
The company expects to produce 400,000 units, with each unit requiring 0.90 direct labor hours.
[tex]\[ \text{Total direct labor hours needed} = 400,000 \text{ units} \times 0.90 \text{ DLH/unit} = 360,000 \text{ DLH} \][/tex]
5. Calculate overhead assigned to each unit:
First, we find the overhead per unit based on the labor hours each unit requires and the plantwide overhead rate.
[tex]\[ \text{Overhead assigned to each unit} = 0.90 \text{ DLH/unit} \times \$12.34 \text{ per DLH} = \$11.11 \text{ per unit} \][/tex]
Therefore, the amount of overhead assigned to each unit produced is \[tex]$11.11 per unit. The correct answer from the options is: \[ \$[/tex]11.11 \text{ per unit}
\]
1. Calculate total manufacturing overhead costs:
The estimated manufacturing overhead costs for Department 1 are \[tex]$2,530,000 and for Department 2 are \$[/tex]900,000.
[tex]\[ \text{Total manufacturing overhead costs} = \$2,530,000 + \$900,000 = \$3,430,000 \][/tex]
2. Calculate total direct labor hours (DLH):
The estimated direct labor hours for Department 1 are 168,000 hours and for Department 2 are 110,000 hours.
[tex]\[ \text{Total direct labor hours} = 168,000 \text{ DLH} + 110,000 \text{ DLH} = 278,000 \text{ DLH} \][/tex]
3. Calculate the plantwide overhead rate:
The plantwide overhead rate is calculated by dividing the total manufacturing overhead costs by the total direct labor hours.
[tex]\[ \text{Plantwide overhead rate} = \frac{\text{Total manufacturing overhead costs}}{\text{Total direct labor hours}} = \frac{\$3,430,000}{278,000 \text{ DLH}} = \$12.34 \text{ per DLH} \][/tex]
4. Calculate total direct labor hours needed for the expected production:
The company expects to produce 400,000 units, with each unit requiring 0.90 direct labor hours.
[tex]\[ \text{Total direct labor hours needed} = 400,000 \text{ units} \times 0.90 \text{ DLH/unit} = 360,000 \text{ DLH} \][/tex]
5. Calculate overhead assigned to each unit:
First, we find the overhead per unit based on the labor hours each unit requires and the plantwide overhead rate.
[tex]\[ \text{Overhead assigned to each unit} = 0.90 \text{ DLH/unit} \times \$12.34 \text{ per DLH} = \$11.11 \text{ per unit} \][/tex]
Therefore, the amount of overhead assigned to each unit produced is \[tex]$11.11 per unit. The correct answer from the options is: \[ \$[/tex]11.11 \text{ per unit}
\]
We value your presence here. Keep sharing knowledge and helping others find the answers they need. This community is the perfect place to learn together. For trustworthy answers, visit IDNLearn.com. Thank you for your visit, and see you next time for more reliable solutions.