Monitoring contractor performance includes a review of progress reports. Which item should the COR NOT check for in a progress report?

A. Whether the contractor is on schedule
B. Whether actual deliveries match what is in the report
C. Whether individual contractor employees are performing to contract standards
D. Whether the expenses match the amount of work performed so far


Sagot :

Final answer:

The COR should not check whether individual Contractor employees are performing to contract standards in a progress report.


Explanation:

What the COR Should NOT Check for in a Progress Report:

Whether individual Contractor employees are performing to contract standards

While reviewing a progress report, the COR should focus on aspects like whether the Contractor is on schedule and if actual deliveries match the report. It is important to track progress and expenses to ensure the project is on track and within budget.


Learn more about Contractor performance evaluation here: