Get the answers you've been looking for with the help of IDNLearn.com's expert community. Discover prompt and accurate responses from our experts, ensuring you get the information you need quickly.

Compute the NPV for Project X and decide whether to accept or reject the project given the cash flows shown below if the appropriate cost of capital is 12 percent.

\begin{tabular}{lcccccc}
\hline Time: & 0 & 1 & 2 & 3 & 4 & 5 \\
\hline Cash flow: & -120 & -120 & 0 & 190 & 165 & 140 \\
\hline
\end{tabular}


Sagot :

Sure, let's compute the Net Present Value (NPV) of Project X step-by-step and determine whether to accept or reject the project given a 12 percent cost of capital.

### Step-by-Step Calculation:

1. Given Data:
- Cash Flows: [tex]\([-120, -120, 0, 190, 165, 140]\)[/tex]
- Cost of Capital ([tex]\(r\)[/tex]) = 12% or 0.12

2. NPV Formula:
[tex]\[ NPV = \sum_{t=0}^{n} \frac{CF_t}{(1 + r)^t} \][/tex]
where [tex]\(CF_t\)[/tex] represents the cash flow at time [tex]\(t\)[/tex], [tex]\(r\)[/tex] is the discount rate, and [tex]\(t\)[/tex] is the time period.

3. Calculate the Present Value of Each Cash Flow:
- For t = 0:
[tex]\[ \frac{-120}{(1 + 0.12)^0} = -120 \][/tex]
- For t = 1:
[tex]\[ \frac{-120}{(1 + 0.12)^1} = \frac{-120}{1.12} \approx -107.14 \][/tex]
- For t = 2:
[tex]\[ \frac{0}{(1 + 0.12)^2} = 0 \][/tex]
- For t = 3:
[tex]\[ \frac{190}{(1 + 0.12)^3} = \frac{190}{1.404928} \approx 135.30 \][/tex]
- For t = 4:
[tex]\[ \frac{165}{(1 + 0.12)^4} = \frac{165}{1.5748016} \approx 104.79 \][/tex]
- For t = 5:
[tex]\[ \frac{140}{(1 + 0.12)^5} = \frac{140}{1.7623411} \approx 79.44 \][/tex]

4. Sum these Present Values:
[tex]\[ NPV = -120 - 107.14 + 0 + 135.30 + 104.79 + 79.44 \approx 92.40 \][/tex]

5. Decision Rule:
- If NPV > 0: Accept the project.
- If NPV < 0: Reject the project.

6. Conclusion:
- NPV [tex]\( \approx 92.40 \)[/tex]
- Since the NPV is positive, we accept Project X.

Therefore, the NPV of Project X is approximately 92.40, and based on this calculation, we should accept the project.