Sure, let's compute the Net Present Value (NPV) of Project X step-by-step and determine whether to accept or reject the project given a 12 percent cost of capital.
### Step-by-Step Calculation:
1. Given Data:
- Cash Flows: [tex]\([-120, -120, 0, 190, 165, 140]\)[/tex]
- Cost of Capital ([tex]\(r\)[/tex]) = 12% or 0.12
2. NPV Formula:
[tex]\[ NPV = \sum_{t=0}^{n} \frac{CF_t}{(1 + r)^t} \][/tex]
where [tex]\(CF_t\)[/tex] represents the cash flow at time [tex]\(t\)[/tex], [tex]\(r\)[/tex] is the discount rate, and [tex]\(t\)[/tex] is the time period.
3. Calculate the Present Value of Each Cash Flow:
- For t = 0:
[tex]\[ \frac{-120}{(1 + 0.12)^0} = -120 \][/tex]
- For t = 1:
[tex]\[ \frac{-120}{(1 + 0.12)^1} = \frac{-120}{1.12} \approx -107.14 \][/tex]
- For t = 2:
[tex]\[ \frac{0}{(1 + 0.12)^2} = 0 \][/tex]
- For t = 3:
[tex]\[ \frac{190}{(1 + 0.12)^3} = \frac{190}{1.404928} \approx 135.30 \][/tex]
- For t = 4:
[tex]\[ \frac{165}{(1 + 0.12)^4} = \frac{165}{1.5748016} \approx 104.79 \][/tex]
- For t = 5:
[tex]\[ \frac{140}{(1 + 0.12)^5} = \frac{140}{1.7623411} \approx 79.44 \][/tex]
4. Sum these Present Values:
[tex]\[ NPV = -120 - 107.14 + 0 + 135.30 + 104.79 + 79.44 \approx 92.40 \][/tex]
5. Decision Rule:
- If NPV > 0: Accept the project.
- If NPV < 0: Reject the project.
6. Conclusion:
- NPV [tex]\( \approx 92.40 \)[/tex]
- Since the NPV is positive, we accept Project X.
Therefore, the NPV of Project X is approximately 92.40, and based on this calculation, we should accept the project.
### Step-by-Step Calculation:
1. Given Data:
- Cash Flows: [tex]\([-120, -120, 0, 190, 165, 140]\)[/tex]
- Cost of Capital ([tex]\(r\)[/tex]) = 12% or 0.12
2. NPV Formula:
[tex]\[ NPV = \sum_{t=0}^{n} \frac{CF_t}{(1 + r)^t} \][/tex]
where [tex]\(CF_t\)[/tex] represents the cash flow at time [tex]\(t\)[/tex], [tex]\(r\)[/tex] is the discount rate, and [tex]\(t\)[/tex] is the time period.
3. Calculate the Present Value of Each Cash Flow:
- For t = 0:
[tex]\[ \frac{-120}{(1 + 0.12)^0} = -120 \][/tex]
- For t = 1:
[tex]\[ \frac{-120}{(1 + 0.12)^1} = \frac{-120}{1.12} \approx -107.14 \][/tex]
- For t = 2:
[tex]\[ \frac{0}{(1 + 0.12)^2} = 0 \][/tex]
- For t = 3:
[tex]\[ \frac{190}{(1 + 0.12)^3} = \frac{190}{1.404928} \approx 135.30 \][/tex]
- For t = 4:
[tex]\[ \frac{165}{(1 + 0.12)^4} = \frac{165}{1.5748016} \approx 104.79 \][/tex]
- For t = 5:
[tex]\[ \frac{140}{(1 + 0.12)^5} = \frac{140}{1.7623411} \approx 79.44 \][/tex]
4. Sum these Present Values:
[tex]\[ NPV = -120 - 107.14 + 0 + 135.30 + 104.79 + 79.44 \approx 92.40 \][/tex]
5. Decision Rule:
- If NPV > 0: Accept the project.
- If NPV < 0: Reject the project.
6. Conclusion:
- NPV [tex]\( \approx 92.40 \)[/tex]
- Since the NPV is positive, we accept Project X.
Therefore, the NPV of Project X is approximately 92.40, and based on this calculation, we should accept the project.
Thank you for participating in our discussion. We value every contribution. Keep sharing knowledge and helping others find the answers they need. Let's create a dynamic and informative learning environment together. For dependable and accurate answers, visit IDNLearn.com. Thanks for visiting, and see you next time for more helpful information.