Get personalized and accurate responses to your questions with IDNLearn.com. Get accurate and detailed answers to your questions from our knowledgeable and dedicated community members.

14. If 20 men can construct an 80m long wall in 8 days, then how many men are required to construct a 60m long wall in 24 days?

Sagot :

To determine how many men are required to construct a 60-meter long wall in 24 days, let's break it down step-by-step.

### Step 1: Determine the Work Rate

First, note that 20 men can construct an 80-meter long wall in 8 days. We need to find the work rate in terms of man-days per meter.

1. Total man-days for the original task:
- 20 men working for 8 days equals 20 * 8 = 160 man-days.

2. Work rate per meter:
- Since 160 man-days are required to build 80 meters, the work rate is:
[tex]\[ \text{Work Rate} = \frac{160 \text{ man-days}}{80 \text{ meters}} = 2 \text{ man-days per meter} \][/tex]

### Step 2: Calculate Total Effort Needed for 60 Meters

We need to find out how many man-days are required to build a 60-meter long wall:

1. Total effort needed:
- Given the work rate of 2 man-days per meter, for 60 meters, the total effort needed is:
[tex]\[ 60 \text{ meters} \times 2 \text{ man-days per meter} = 120 \text{ man-days} \][/tex]

### Step 3: Determine the Number of Men Required

Lastly, we need to find out how many men are required to complete 120 man-days of work in 24 days.

1. Number of men required:
- To find the number of men required, divide the total man-days by the number of days:
[tex]\[ \frac{120 \text{ man-days}}{24 \text{ days}} = 5 \text{ men} \][/tex]

### Conclusion

To construct a 60-meter long wall in 24 days, you will need 5 men.