IDNLearn.com: Where your questions meet expert answers and community support. Our experts are ready to provide in-depth answers and practical solutions to any questions you may have.
Sagot :
To determine how many men are required to construct a 60-meter long wall in 24 days, let's break it down step-by-step.
### Step 1: Determine the Work Rate
First, note that 20 men can construct an 80-meter long wall in 8 days. We need to find the work rate in terms of man-days per meter.
1. Total man-days for the original task:
- 20 men working for 8 days equals 20 * 8 = 160 man-days.
2. Work rate per meter:
- Since 160 man-days are required to build 80 meters, the work rate is:
[tex]\[ \text{Work Rate} = \frac{160 \text{ man-days}}{80 \text{ meters}} = 2 \text{ man-days per meter} \][/tex]
### Step 2: Calculate Total Effort Needed for 60 Meters
We need to find out how many man-days are required to build a 60-meter long wall:
1. Total effort needed:
- Given the work rate of 2 man-days per meter, for 60 meters, the total effort needed is:
[tex]\[ 60 \text{ meters} \times 2 \text{ man-days per meter} = 120 \text{ man-days} \][/tex]
### Step 3: Determine the Number of Men Required
Lastly, we need to find out how many men are required to complete 120 man-days of work in 24 days.
1. Number of men required:
- To find the number of men required, divide the total man-days by the number of days:
[tex]\[ \frac{120 \text{ man-days}}{24 \text{ days}} = 5 \text{ men} \][/tex]
### Conclusion
To construct a 60-meter long wall in 24 days, you will need 5 men.
### Step 1: Determine the Work Rate
First, note that 20 men can construct an 80-meter long wall in 8 days. We need to find the work rate in terms of man-days per meter.
1. Total man-days for the original task:
- 20 men working for 8 days equals 20 * 8 = 160 man-days.
2. Work rate per meter:
- Since 160 man-days are required to build 80 meters, the work rate is:
[tex]\[ \text{Work Rate} = \frac{160 \text{ man-days}}{80 \text{ meters}} = 2 \text{ man-days per meter} \][/tex]
### Step 2: Calculate Total Effort Needed for 60 Meters
We need to find out how many man-days are required to build a 60-meter long wall:
1. Total effort needed:
- Given the work rate of 2 man-days per meter, for 60 meters, the total effort needed is:
[tex]\[ 60 \text{ meters} \times 2 \text{ man-days per meter} = 120 \text{ man-days} \][/tex]
### Step 3: Determine the Number of Men Required
Lastly, we need to find out how many men are required to complete 120 man-days of work in 24 days.
1. Number of men required:
- To find the number of men required, divide the total man-days by the number of days:
[tex]\[ \frac{120 \text{ man-days}}{24 \text{ days}} = 5 \text{ men} \][/tex]
### Conclusion
To construct a 60-meter long wall in 24 days, you will need 5 men.
Thank you for being part of this discussion. Keep exploring, asking questions, and sharing your insights with the community. Together, we can find the best solutions. IDNLearn.com is your source for precise answers. Thank you for visiting, and we look forward to helping you again soon.