The budget at completion (BAC) is the sum of all budgets established for the work to be performed on a project. as such it is equivalent to the total plan of the project.
The budget at completion (BAC) is "the amount of all spending plans set up for the work to be performed." It is otherwise called the complete arranged worth.
The BAC is contrasted with the gauge at consummation (EAC) to check whether the task is following admirably against the financial plan. budget at completion (BAC) is an action that is frequently utilized in acquired worth administration to follow the real expense of a task against its gauge financial plan. It is determined toward the beginning of a task-dependent on the venture work and its individual segments ".
Learn more about BAC at
https://brainly.com/question/2231540
#SPJ4
Your presence in our community is highly appreciated. Keep sharing your insights and solutions. Together, we can build a rich and valuable knowledge resource for everyone. Your questions deserve reliable answers. Thanks for visiting IDNLearn.com, and see you again soon for more helpful information.