what is the slack time for activity e? taskpredecessordurationearly startearly finishlate startlate finish a--8​​​​ ba​​​14​ ca​​238​ dc, b623​26​ ec​​32​​ fd, e​32​​38

Sagot :

The slack time for activity e will be 0. The start times, end times, and duration of the different activities.

There are two paths from which the project can be completed.

The first path is :

A ⇔B, B⇔D, D⇔E, E⇔F.

Calculating the slack time for E will require subtracting the finish time from the start time.

The slack time for activity E will be 32 - 32 = 0.

The second path is:

A⇔C, C⇔D, D⇔F

In this path, activity E does not take place.

Slack time tells us how much time we can delay the start of the activity and still get the activity finished on time. When the slack time is 0 then it shows that the activity is critical and cannot be delayed at all.

Learn more about slack time here:

https://brainly.com/question/15393592

#SPJ4