Get personalized answers to your unique questions on IDNLearn.com. Join our community to receive prompt and reliable responses to your questions from experienced professionals.
Sagot :
To solve this problem, we need to break it down into calculable parts and follow a systematic approach.
### Step 1: Determine the work rate of one man and one woman
1. Work rate of one man:
- 16 men can complete the project in 20 days.
- Therefore, the amount of work one man can complete in one day is [tex]\( \frac{1}{16 \times 20} \)[/tex].
- This simplifies to [tex]\( \frac{1}{320} \)[/tex] of the work per day.
2. Work rate of one woman:
- 14 women can complete the project in 30 days.
- Therefore, the amount of work one woman can complete in one day is [tex]\( \frac{1}{14 \times 30} \)[/tex].
- This simplifies to [tex]\( \frac{1}{420} \)[/tex] of the work per day.
### Step 2: Calculate the work done by 40 men in 5 days
1. Work rate for 40 men:
- Work rate of one man is [tex]\( \frac{1}{320} \)[/tex].
- Work rate of 40 men is [tex]\( 40 \times \frac{1}{320} \)[/tex].
- This simplifies to [tex]\( \frac{40}{320} = \frac{1}{8} \)[/tex] of the work per day.
2. Work completed by 40 men in 5 days:
- [tex]\( \frac{1}{8} \)[/tex] of the work per day.
- In 5 days, the work completed is [tex]\( 5 \times \frac{1}{8} = \frac{5}{8} \)[/tex] of the work.
### Step 3: Determine the remaining work
1. Total work needed to complete the project is assumed to be 1 unit.
2. Work completed by 40 men in 5 days is [tex]\( \frac{5}{8} \)[/tex].
3. Remaining work:
- [tex]\( 1 - \frac{5}{8} = \frac{3}{8} \)[/tex] of the work is still remaining.
### Step 4: Calculate the number of days 21 women need to complete the remaining work
1. Work rate for 21 women:
- Work rate of one woman is [tex]\( \frac{1}{420} \)[/tex].
- Work rate of 21 women is [tex]\( 21 \times \frac{1}{420} \)[/tex].
- This simplifies to [tex]\( \frac{21}{420} = \frac{1}{20} \)[/tex] of the work per day.
2. Days needed for 21 women to complete the remaining [tex]\( \frac{3}{8} \)[/tex] of the work:
- [tex]\( \frac{3}{8} \)[/tex] of the work remaining and the work rate of 21 women is [tex]\( \frac{1}{20} \)[/tex] per day.
- Number of days = [tex]\( \frac{\frac{3}{8}}{\frac{1}{20}} = \frac{3}{8} \times 20 = \frac{60}{8} = 7.5 \)[/tex] days.
### Conclusion
The number of days in which the 21 women can finish the remaining work is 7.5 days.
### Step 1: Determine the work rate of one man and one woman
1. Work rate of one man:
- 16 men can complete the project in 20 days.
- Therefore, the amount of work one man can complete in one day is [tex]\( \frac{1}{16 \times 20} \)[/tex].
- This simplifies to [tex]\( \frac{1}{320} \)[/tex] of the work per day.
2. Work rate of one woman:
- 14 women can complete the project in 30 days.
- Therefore, the amount of work one woman can complete in one day is [tex]\( \frac{1}{14 \times 30} \)[/tex].
- This simplifies to [tex]\( \frac{1}{420} \)[/tex] of the work per day.
### Step 2: Calculate the work done by 40 men in 5 days
1. Work rate for 40 men:
- Work rate of one man is [tex]\( \frac{1}{320} \)[/tex].
- Work rate of 40 men is [tex]\( 40 \times \frac{1}{320} \)[/tex].
- This simplifies to [tex]\( \frac{40}{320} = \frac{1}{8} \)[/tex] of the work per day.
2. Work completed by 40 men in 5 days:
- [tex]\( \frac{1}{8} \)[/tex] of the work per day.
- In 5 days, the work completed is [tex]\( 5 \times \frac{1}{8} = \frac{5}{8} \)[/tex] of the work.
### Step 3: Determine the remaining work
1. Total work needed to complete the project is assumed to be 1 unit.
2. Work completed by 40 men in 5 days is [tex]\( \frac{5}{8} \)[/tex].
3. Remaining work:
- [tex]\( 1 - \frac{5}{8} = \frac{3}{8} \)[/tex] of the work is still remaining.
### Step 4: Calculate the number of days 21 women need to complete the remaining work
1. Work rate for 21 women:
- Work rate of one woman is [tex]\( \frac{1}{420} \)[/tex].
- Work rate of 21 women is [tex]\( 21 \times \frac{1}{420} \)[/tex].
- This simplifies to [tex]\( \frac{21}{420} = \frac{1}{20} \)[/tex] of the work per day.
2. Days needed for 21 women to complete the remaining [tex]\( \frac{3}{8} \)[/tex] of the work:
- [tex]\( \frac{3}{8} \)[/tex] of the work remaining and the work rate of 21 women is [tex]\( \frac{1}{20} \)[/tex] per day.
- Number of days = [tex]\( \frac{\frac{3}{8}}{\frac{1}{20}} = \frac{3}{8} \times 20 = \frac{60}{8} = 7.5 \)[/tex] days.
### Conclusion
The number of days in which the 21 women can finish the remaining work is 7.5 days.
Your engagement is important to us. Keep sharing your knowledge and experiences. Let's create a learning environment that is both enjoyable and beneficial. Find precise solutions at IDNLearn.com. Thank you for trusting us with your queries, and we hope to see you again.